Sunday, October 21, 2012

This week, A. Lamp Concrete Contractors installed the posts for the chain link fence and guard rail.

Next week, the contractor is scheduled to complete the chain link fence and guard rail installation.  The contractor is also anticipating to pour the concrete sidewalk.

There will be no full ramp closures throughout the duration of the project.  However, there may be instance when getting around this area will be difficult due to  construction operations.

Thank you in advance for your patience during this construction project.